NB: Our first service in the new sanctuary will be in January... we hope!
Have you ever wondered how many hours are invested in remodeling and construction our building?
- Jacob Perkins, a Milo Construction employee, has spent 1,097 hours since the beginning of the project. This week he was in charge of cleanup and trash removal.
- KC Drywall has drywalled the lobby area and the south wing. They have taped and mudded the west wing: 352 hours so far.
- Major Mechanical has been building mechanical ducting for heat pumps and ERVs (Energy Recovery Ventilator). They have also insulated all of the mechanical ducting: 1,638 hours.
- Mountain Insulation has insulated the lobby area and kitchen walls and blew in the sanctuary ceiling: 505 hours.
- Mountain States Framing: Finished tongue and groove on clerestory windows in the sanctuary and started on the siding outside of the sanctuary: 3,450 hours.
Total number of hours for all contractors: 14,995.25.
To view the latest video of the remodeling and construction, click here: Race to the Finish Line.