The Building Committee has decided to
POSTPONE
this Sunday's Walk-Through at the Fellowship.
The snow, mud, ice, hidden curbs and inclement weather would make for a dangerous trek to get to the entrance of the building. In addition, tracking mud onto the new carpeting and tile is not a good idea.
We will happily inform you of a new date for the Walk-Through as soon as the weather allows.
Be resilient!
At the Fellowship this week contractors are:
- Finishing nosing on dais steps
- Starting hardwood floor on dais
- Touching up paint around the building
- Cleaning up the site
- Shoveling snow from sidewalks
- Fixing errors in tongue & groove.
- Erasing pencil marks on wood
- Trimming out electrical around the building
- Trimming out the janitors closet
- Installing toilets, sinks and a water faucet
20,311
Number of hours that our contractors have spent working on the Fellowship.