Week #40 at the building site was a busy one:


  • Getting parking lots up to grade for asphalt.  Soon!  
  • Preparing for curb and gutters.
  • Cleaning up the site. 
  • Demo-ing the doorway in the Fellowship Hall so hollow metal frame would fit.
  • Sanding, taping and mudding on walls in the Admin Wing (the old RE Wing).
  • Installing drop ceiling for ACT (Acoustic Ceiling Tiles).
  • Installing hardware on doors in new School of Spirit (SOS) Wing.
Occupancy in January 2020... we hope!