Thursday, January 9, 2020

Week 48 - A Work In Progress



A busy week inside the Fellowship building:

  1. Painting walls and ceiling of Fellowship Hall
  2. Cleaning up the job site  and removing trash
  3. Sanding and mudding in the mechanical room and storage room
  4. Checking heat pumps and ERVs to make sure they are set up correctly
  5. Attaching tongue and grove, beetle kill pine, in the sanctuary and south east entry vestibule
  6. Setting up the low voltage/audio visual room
  7. Installing a storefront frame on storage room
  8. Installing lights and remodel cans around building  
    • NB:  ceiling light switches are motion sensitive!
  9. Wiring up fixtures in lobby area
  10. Painting storage rooms and finishing lacquer on tongue and groove ceiling in sanctuary

Number of hours that our contractor and sub-contractors have put in so far:  

18,071 hours


Click here for the latest Building Committee Video Clip entitled:


  A Work In Progress