Building Project Construction Status
- Installing access panels in the ceiling
- Cleaning up the site
- Making sure that the hydrothermal system is running correctly
- Trimming out mechanical system
- Installing lights in lobby and Fellowship Hall
- Installing vent grills
- Removing concrete blankets from sidewalks
- Installing electrical trim in kitchen
- Preparing stucco to receive cap around radius wall
- Installing marmoleum flooring in classrooms, kitchen, & kitchenette
- Grading exterior to prepare for hardscape
21,174.25
Number of hours contractors have worked on our project.
To view the latest Building Committee video clip of the progress the contractors are making on our remodeling and construction project
CLICK HERE: