Thursday, April 30, 2020

Week 64 - Spic 'n Span


BVUUF Building Project Construction Status

This was the week of deep cleaning.  Now, the entire interior is spic 'n span.

The landscapers continue with their work outside.  New trees and shrubs have been planted, a sprinkler system is being installed, and we provided one of the neighbors with a privacy fence on the south side of the site.

22,797

The number of hours our contractor and sub-contractors have spent on this project.

Click here to see our construction progress video entitled