Week 41:
FIRST SERVICE IN THE NEW SANCTUARY AT THE FELLOWSHIP IS
FEBRUARY 9TH AT 10 AM.
WEATHER PERMITTING!
Who's doing what this week?
- Jacob, on-site supervisor assistant: Cleaning up site and demoing doorway on end of south wing.
- KC Drywall: Installing drywall in cuddle room and sanctuary.
- Major Mechanical: Tying ducting into ground source heat pumps next to cuddle room .
- R & R Concrete: Forming cross pans for vehicle entry of parking lots.
- Shade Glass: Setting frames for exterior door in south wing and double doors in the lobby area.
- South Paw Electric: Running conduit and setting light fixtures behind dais in sanctuary.
Total number of man-hours invested in the remodeling and construction of the Fellowship: 15,870.00
To view the week 41 video clip of Fellowship construction,