Another busy week ..... inside the building. Too much mud still to work much outside.
Some of the activities that subcontractors worked on this week:
- Starting stucco application on exterior
- Spraying another layer of paint in lobby area ceiling, bathrooms and clerestory
- Site cleanup and unloading ceiling tiles
- Installing ceiling tile in the School of the Spirit (SOS) wing
- Hanging sheetrock in the sanctuary on walls and over the dais
- Building a hydrothermal mechanical room
- Wiring up heat pumps in classrooms
- Installing wiring for all the lights in the SOS wing and sanctuary
This week's Building Committee video clip of construction progress is entitled
to view, click the title.