Thursday, February 27, 2020

Week 55 - Wrapping Up

The Building Committee is ecstatic to announce that we have scheduled the long-awaitedWalk-Through/Open House at the newly-refurbished Fellowship building for members on:
  • Sunday
  • March 8th
  • 10 am - 11:30 am  
    • Don't forget: this is the first day of Daylight Savings Time.
Members of the Building Committee and the Design Team will be available to answer your questions.

You will need to park on the street, as we don't have a paved parking lot ... yet.  Please be mindful not to block any of the neighbors' driveways. 

Enter through the gate on the east side of the Fellowship (Ceres Drive) and proceed on our brand new sidewalks to the main entrance.  

Building Project Construction Status

  • Significant Milestones
    • Interior finishing nearly complete
    • Stucco & painting nearing completion
    • HVAC startup underway
    • Landscaping postponed to spring
    • Parking lot paving weather delay until early spring - will delay occupancy
  • Other Major Activities This Month
    • Continuing floor tile and carpet installation
    • Cabinets installed in kitchen
    • Bathroom fixtures installed
    • Finishing painting interior & exterior
    • Gutters installed
    • Dais work nearly complete
    • Hearing loops installed
20, 782.25

Number of hours contractors have worked on our project.