Monday, August 26, 2019

Week 29 - Construction Status - mid July - mid August


BVUUF Building Project Construction Status
July 2019 (mid-July to mid-August)

This report covers mid-month to mid-month.

Significant Milestones
  •   Framing basically complete
  •   Xcel finally ready to install electric power
  •   Exterior siding installed
  •   Windows installed

  • Other Major Activities This Month

  •   Grading and curbing of parking lots nearly complete
  •   Roughing utilities work nearing completion: HVAC ducts, plumbing, electrical,
    low voltage conduit, interior sprinkler system
  •   Finishing foundations for parking lot lights
  •   Comcast/Xfinity access trench/conduit complete
  •   Excess dirt removal complete
  •   Landscape sprinkler system being installed (not complete)

  • Major Activities Next Month
  •   Roofing
  •   Interior dry wall
  •   Storm water pipe to South Boulder to begin 8/19
  •   Interior utilities work continues
  •   Ground source heat pump system equipment to be delivered
  •   Xcel electric installation

Thursday, August 22, 2019

Abbreviations

Construction Week 28 

Click here to see the latest Building Committee Video Clip:  Abbreviations.

Friday, August 16, 2019

Dias? Days? Diaz? Dais?

Construction Week 27:

We've posted the latest video clip to bring members up to date on construction progress at the Fellowship.  Click here:  Dias? Days? Diaz? Dais?

Thursday, August 8, 2019