BVUUF Building Project Construction Status
July 2019 (mid-July to mid-August)
This report covers mid-month to mid-month.
Significant Milestones
-
Framing basically complete
-
Xcel finally ready to install electric power
- Exterior siding installed
- Windows installed
- Other Major Activities This Month
-
Grading and curbing of parking lots nearly complete
-
Roughing utilities work nearing completion: HVAC ducts, plumbing, electrical,
low voltage conduit, interior sprinkler system
-
Finishing foundations for parking lot lights
-
Comcast/Xfinity access trench/conduit complete
- Excess dirt removal complete
- Landscape sprinkler system being installed (not complete)
- Major Activities Next Month
-
Roofing
-
Interior dry wall
-
Storm water pipe to South Boulder to begin 8/19
-
Interior utilities work continues
-
Ground source heat pump system equipment to be delivered
-
Xcel electric installation