- Continuing building forms and setting rebar in foundation wall.
- Continuing on fire line from street.
- Moving dirt to stockpile.
- Drilling first well for Ground Source Heating Pump (GSHP) to put under testing. Once drilled in, must sit for 5 days then a heat test is run for 2 days. After the results come back from testing, they can continue drilling the remaining 9 holes.
- Removing old insulation from the sanctuary.
Blog of the Building Committee of the Boulder Valley Unitarian Universalist Fellowship in Lafayette, CO, USA.
Friday, April 19, 2019
Week 10: Lots Of Progress!
Here's what the contractors did this week: