Week 35 -Pipes and Pipers
Lots of progress in the ceiling and behind the walls
- Jacob (On-Site Supervisor) is doing general cleanup, and getting the blue storage container ready to move out.
- The mechanical guys are doing some final punch out items for tomorrow’s inspection. Their insulation contractor is wrapping all of the mechanical water pipes.
- The electricians are wiring the dais to be ready for the carpenters to sheet the stage. They are also installing light fixtures in the sanctuary.
- Jacob has been rolling up all of the fire hoses and cold protection for water risers.
- The guys are sealing up all of the ductwork in the sanctuary and removing extra materials.
- The crews are insulating the walls in the classroom wing.
- The electricians are pulling the home runs for panel A and making up outlets for permanent power.
To view the Week 35 video clip, click here: Pipes and Pipers
Thursday, October 3, 2019
Week 34 - East Detention Pond and West Parking Lot
The latest Building Committee video clip is available for viewing. Please click here to view
Week 34 - Will the circle be unbroken?
Week 34 - Will the circle be unbroken?
Thursday, September 26, 2019
Week 33 - MACHINES
Click here to view the video clip of Week 33: MACHINES: Construction and Remodeling of the Fellowship.
Subscribe to: