Saturday, April 6, 2019

Building Project Construction Status


Week 8
Significant Milestones:
  • Concrete footings for sanctuary and RE wing ready to pour next week.
  • Demolition is finished (mostly).
  • Trees and brush are removed and grading is underway.
  • The barn was moved and will be moved again to a permanent concrete pad.





Issues:

  • Waiting for Xcel to demo the gas line and install new electric service.
  • After a meeting with the HVAC contractor, there may be a redesign of the duct work in the admin wing.  The old ducts are not appropriate for use.
  • Schedule is still green which means on-schedule.




Next Month:
  • Ground source heat pump (GSHP) drilling will begin. (Goodbye natural gas!)
  • Will dig retention ponds. (Might lose 1 of the big pine trees.)
  • Pouring of concrete footing will continue.


Friday, March 22, 2019

Footing Excavation and Site Clearing in the South Parking Lot

  1. Rolled out the water meter and hoses and at the end of day pulled them all in and secured the meter. 
  2. Conducted the stormwater perimeter walk.
  3. Removed tree at corner of north classroom wing.
  4. Continuing on compacting and fine grading of the footing trench bottom.