Wednesday, January 1, 2020

Week 47 - Construction Progress:


  • HVAC technicians working on the heating and air conditioning system
  • Carpenters installing beetle kill pine in the sanctuary ceiling
  • Sheet rock folks installing and finishing walls and ceiling in the Fellowship Hall
  • Electricians  installing electrical outlets throughout the building
  • Continual clean up of trash around the site
  • Technicians prepping the outside of the building for stucco application

For the Building Committee's latest video clip of construction progress:

click here:  

Thursday, December 26, 2019

Week 46: 2019 In Retrospect


This is the Work Log for last week at the Fellowship:

  • Advanced Stucco Design:  applying mesh to the sanctuary exterior
  • Denver Tile & Stone:  tiling the lobby
  • Milo Construction:  cleaning the site and laying floor protection on tile and carpeting
  • Jagger Roofing:  finishing flatroof flashing
  • KC Drywall:  continuing to drywall the Fellowship
  • Major Mechanical:   completing the installation of the heat pumps
  • Mountain States Framing:  installing tongue & groove beetle kill pine on sanctuary ceiling
  • R & R Concrete:  organizing wood planks from curb and cross pans
  • Slade Glass:  installing main entrance doors
  • South Paw Electric:  continuing work to install electrical outlets
Total number of hours to date of work on the Fellowship:  

17,467 Hours!  


Click here for the latest Building Committee Video Clip entitled:  2019 In Retrospect.

Thursday, December 19, 2019

Week 45 - A Mini-Mobile Momentous Moment

BVUUF Building Project Construction Status

Significant Milestones

  • Interior finishing work is ongoing
  • Exterior work is slowed by cold weather
  • Landscaping postponed until spring
Other Major Activities This Month
  • Starting stucco application & painting on exterior
  • Spraying another layer of paint in lobby area ceiling, bathrooms and clerestory
  • Installing ceiling tile in the School of the Spirit (SOS) wing
  • Hanging sheetrock in the sanctuary on walls and over the dais
  • Building a hydrothermal mechanical room
  • Wiring up heat pumps in classrooms
  • Starting beetle kill ceiling in Sanctuary
  • Starting floor tile and carpet installation
Parking Lot Paving Issues
  • Both wet & frozen soils are issues
    • Soil is frozen 12" below the surface
  • The Building Committee continues to aggressively monitor the situation and consider alternatives.
This week's Building Committee video clip of construction progress is entitled


to view, click the title above.

Thursday, December 12, 2019

Week 44 - My Hanukkah

Week 44

Another busy week ..... inside the building. Too much mud still to work much outside.

Some of the activities that subcontractors worked on this week:
  • Starting stucco application on exterior
  • Spraying another layer of paint in lobby area ceiling, bathrooms and clerestory 
  • Site cleanup and unloading ceiling tiles
  • Installing ceiling tile in the School of the Spirit (SOS) wing
  • Hanging sheetrock in the sanctuary on walls and over the dais
  • Building a hydrothermal mechanical room
  • Wiring up heat pumps in classrooms
  • Installing wiring for all the lights in the SOS wing and sanctuary
This week's Building Committee video clip of construction progress is entitled


to view, click the title.