Thursday, February 6, 2020

Week 52 Finishing Touches II - Trailer


The Building Committee has decided to 
POSTPONE 
this Sunday's Walk-Through at the Fellowship.

The snow, mud, ice, hidden curbs and inclement weather would make for a dangerous trek to get to the entrance of the building.  In addition, tracking mud onto the new carpeting and tile is not a good idea.

We will happily inform you of a new date for the Walk-Through as soon as the weather allows.
Be resilient!     

At the Fellowship this week contractors are:
  1. Finishing nosing on dais steps
  2. Starting hardwood floor on dais
  3. Touching up paint around the building
  4. Cleaning up the site
  5. Shoveling snow from sidewalks
  6. Fixing errors in tongue & groove.
  7. Erasing pencil marks on wood
  8. Trimming out electrical around the building
  9. Trimming out the janitors closet
  10. Installing toilets, sinks and  a water faucet
20,311
Number of hours that our contractors have spent working on the Fellowship.

Click here for the latest Building Committee Video Clip entitled:

Finishing Touches II - Trailer