Thursday, December 12, 2019

Week 44 - My Hanukkah

Week 44

Another busy week ..... inside the building. Too much mud still to work much outside.

Some of the activities that subcontractors worked on this week:
  • Starting stucco application on exterior
  • Spraying another layer of paint in lobby area ceiling, bathrooms and clerestory 
  • Site cleanup and unloading ceiling tiles
  • Installing ceiling tile in the School of the Spirit (SOS) wing
  • Hanging sheetrock in the sanctuary on walls and over the dais
  • Building a hydrothermal mechanical room
  • Wiring up heat pumps in classrooms
  • Installing wiring for all the lights in the SOS wing and sanctuary
This week's Building Committee video clip of construction progress is entitled


to view, click the title.