Thursday, August 29, 2019

Week 29 BVUUF Construct: "Infrastructure"

View the infrastructure of the new and remodeled Fellowship.  Soon it will be covered up and you will never see it again.

Click here for this weeks video clip entitled Infrastructure.

Monday, August 26, 2019

Week 29 - Construction Status - mid July - mid August


BVUUF Building Project Construction Status
July 2019 (mid-July to mid-August)

This report covers mid-month to mid-month.

Significant Milestones
  •   Framing basically complete
  •   Xcel finally ready to install electric power
  •   Exterior siding installed
  •   Windows installed

  • Other Major Activities This Month

  •   Grading and curbing of parking lots nearly complete
  •   Roughing utilities work nearing completion: HVAC ducts, plumbing, electrical,
    low voltage conduit, interior sprinkler system
  •   Finishing foundations for parking lot lights
  •   Comcast/Xfinity access trench/conduit complete
  •   Excess dirt removal complete
  •   Landscape sprinkler system being installed (not complete)

  • Major Activities Next Month
  •   Roofing
  •   Interior dry wall
  •   Storm water pipe to South Boulder to begin 8/19
  •   Interior utilities work continues
  •   Ground source heat pump system equipment to be delivered
  •   Xcel electric installation