Week 58 - The Irony of it All!


The parking lots are complete.  The cleaning crew has started on the interior and the stucco work will be completed this week.  There are other items to be finished up or touched up, but we are getting close.  We are ready for the inspectors from the city to check out all of our systems.

However, the city offices have shut down and inspections not already done have been cancelled.  We don't know what impact this will have yet.  The city did inspect the electrical outlets in the SOS wing and the fire department inspector was scheduled. 

Oh, the irony of it all!

Significant Milestones

• Parking lot paving & striping complete
• Concrete curbs & sidewalks completed
• Stucco rework & painting nearly complete

Other Major Activities This Month

• HVAC balancing ongoing
• Completed floor tile and carpet installation
• Cabinets installed in kitchen
• New chairs for sanctuary received
• Kitchen appliances installed
• Bathroom fixtures installed
• Finish touch up painting interior & exterior
• Gutters installed
• Dais work complete—lighting changes under review
• Final commercial cleaning underway

22,038
Number of hours our contractors have put in working at the Fellowship.