Saturday, May 18, 2019

Week 13 - The Fellowship gains a sound foundation.

RE and Sanctuary Stem Walls (video clip below)

Significant Milestones
  • Stem walls for sanctuary & RE wing poured
  • Detention ponds grading complete
  • Ground source heat pump (GSHP) drilling completed:  10 tubes, each 400 feet deep
  • Xcel demolition complete
Other Major Activities this Month:
  • Barn concrete pad poured
  • RE wing backfilled with dirt and water proofed (see video clip below)
  • GSHP piping installed & trenches covered
  • City inspections to date passed
  • Xcel electric & gas service demo complete
  • Utilities work & tie-in nearly complete
  • Underground plumbing started
Major Activities Next Month:
  • Sanctuary backfilled with dirt & water proofing (see video clip below
  • Lumber & steel delivered May 20-21
  • Framing to begin May 23
  • Structural steel for sanctuary begins May 23
  • Underground plumbing and slab pour preparation

Week 13 Video Clip