Friday, March 22, 2019

Footing Excavation and Site Clearing in the South Parking Lot

  1. Rolled out the water meter and hoses and at the end of day pulled them all in and secured the meter. 
  2. Conducted the stormwater perimeter walk.
  3. Removed tree at corner of north classroom wing.
  4. Continuing on compacting and fine grading of the footing trench bottom.