Timeline

April 23, 2017  

    • Town Hall meeting #1 at 12:15 PM:

May 2017

    • Discussion:  We will discuss our work to date, outline the building requirements we have gathered from many sources, and discuss priorities.

May 22, 2017

    • Town Hall meeting #2 at 12:15pm:
    • Discuss our Stay/Go decision information.

May 23, 2017

    • Board meeting
      • Board to vote on Building Committee’s Stay/Go recommendation.
      • Board vote also needed on initial funding for architectural work (around $50,000).
      • Vote could be contingent on congregational vote at the annual meeting. Late September or Early October

End of May, 2017

    • Choose the Architect

Late September/Early October 2017

    • Capital Campaign Feasibility Study:  We need to run our capital campaign feasibility in late September or early October if we want to do a capital campaign next spring.

June 2017

    • Architectural Work:  Therefore, we need to get architectural work started as early in June as possible, right after the congregational vote, to have concept drawings and cost estimates to use in the feasibility study.

June 3, 2017

    • Annual Congregational Meeting
      • Congregational vote on Stay/Go decision

July 2017

    • Board Meeting
      • Vote on conducting the capital campaign feasibility study & budget for that.

Early September 2017

    • Town Hall #3
      • Presentation of architectural building concepts prior to the feasibility study.

Late September/Early October 2017

    • Capital Campaign Feasibility Study