Building Project Construction Status

  1. Applying exterior stucco
  2. Touching up paint around building 
  3. Painting doors leading into the Fellowship Hall
  4. Cleaning up job site
  5. Removing ram board from atop the floors
  6. Balancing hydrothermal and mechanical systems
  7. Installing break metal on sides of exterior windows
  8. Trimming out the doors in the vestibules
  9. Running wire for light poles in parking lots
  10. Setting up to install parking lot lights
  11. Installing sink in toilet room
  12. Trimming out women's bathroom
  13. Applying last coat of paint on walls.
  14. Installing appliances in kitchen
21,894.25
Number of hours contractors have worked on our project.

To view the latest Building Committee video clip of the progress the contractors are making on our remodeling and construction project click here:

Thursday, March 5, 2020

Week 56 - Remember?

Building Project Construction Status

  1. Installing access panels in the ceiling
  2. Cleaning up the site
  3. Making sure that the hydrothermal system is running correctly
  4. Trimming out mechanical system
  5. Installing lights in lobby and Fellowship Hall
  6. Installing vent grills
  7. Removing concrete blankets from sidewalks
  8. Installing electrical trim in kitchen
  9. Preparing stucco to receive cap around radius wall
  10. Installing marmoleum flooring in classrooms, kitchen, & kitchenette
  11. Grading exterior to prepare for hardscape
21,174.25

Number of hours contractors have worked on our project.

To view the latest Building Committee video clip of the progress the contractors are making on our remodeling and construction project

CLICK HERE:



Thursday, February 27, 2020

Week 55 - Wrapping Up

The Building Committee is ecstatic to announce that we have scheduled the long-awaitedWalk-Through/Open House at the newly-refurbished Fellowship building for members on:
  • Sunday
  • March 8th
  • 10 am - 11:30 am  
    • Don't forget: this is the first day of Daylight Savings Time.
Members of the Building Committee and the Design Team will be available to answer your questions.

You will need to park on the street, as we don't have a paved parking lot ... yet.  Please be mindful not to block any of the neighbors' driveways. 

Enter through the gate on the east side of the Fellowship (Ceres Drive) and proceed on our brand new sidewalks to the main entrance.  

Building Project Construction Status

  • Significant Milestones
    • Interior finishing nearly complete
    • Stucco & painting nearing completion
    • HVAC startup underway
    • Landscaping postponed to spring
    • Parking lot paving weather delay until early spring - will delay occupancy
  • Other Major Activities This Month
    • Continuing floor tile and carpet installation
    • Cabinets installed in kitchen
    • Bathroom fixtures installed
    • Finishing painting interior & exterior
    • Gutters installed
    • Dais work nearly complete
    • Hearing loops installed
20, 782.25

Number of hours contractors have worked on our project.

To view the latest Building Committee video clip of the progress the contractors are making on our remodeling and construction project
click here:  

Thursday, February 20, 2020

Week 54 - The Long Wait

At the Fellowship this week, contractors are:

  1. Patching walls where errors were made
  2. Purging the thermal system
  3. Installing sound panels on the dais by the altar
  4. Checking the electrical circuits
  5. Hooking up insta-hot dispensers in the kitchen
  6. Hooking up the sinks in the men's and women's restroom
20, 642.24

Number of hours contractors have worked on our project.

To view the latest Building Committee video clip of the progress the contractors are making on our remodeling and construction project