Thursday, March 19, 2020

Week 58 - The Irony of it All!


The parking lots are complete.  The cleaning crew has started on the interior and the stucco work will be completed this week.  There are other items to be finished up or touched up, but we are getting close.  We are ready for the inspectors from the city to check out all of our systems.

However, the city offices have shut down and inspections not already done have been cancelled.  We don't know what impact this will have yet.  The city did inspect the electrical outlets in the SOS wing and the fire department inspector was scheduled. 

Oh, the irony of it all!

Significant Milestones

• Parking lot paving & striping complete
• Concrete curbs & sidewalks completed
• Stucco rework & painting nearly complete

Other Major Activities This Month

• HVAC balancing ongoing
• Completed floor tile and carpet installation
• Cabinets installed in kitchen
• New chairs for sanctuary received
• Kitchen appliances installed
• Bathroom fixtures installed
• Finish touch up painting interior & exterior
• Gutters installed
• Dais work complete—lighting changes under review
• Final commercial cleaning underway

22,038
Number of hours our contractors have put in working at the Fellowship.

Click here to see our 58th video clip of construction progress on the Fellowship:


Thursday, March 12, 2020

Week 57 - Final Daze

BVUUF
Building Project Construction Status

  1. Applying exterior stucco
  2. Touching up paint around building 
  3. Painting doors leading into the Fellowship Hall
  4. Cleaning up job site
  5. Removing ram board from atop the floors
  6. Balancing hydrothermal and mechanical systems
  7. Installing break metal on sides of exterior windows
  8. Trimming out the doors in the vestibules
  9. Running wire for light poles in parking lots
  10. Setting up to install parking lot lights
  11. Installing sink in toilet room
  12. Trimming out women's bathroom
  13. Applying last coat of paint on walls.
  14. Installing appliances in kitchen
21,894.25
Number of hours contractors have worked on our project.

To view the latest Building Committee video clip of the progress the contractors are making on our remodeling and construction project click here:

Thursday, March 5, 2020

Week 56 - Remember?

Building Project Construction Status

  1. Installing access panels in the ceiling
  2. Cleaning up the site
  3. Making sure that the hydrothermal system is running correctly
  4. Trimming out mechanical system
  5. Installing lights in lobby and Fellowship Hall
  6. Installing vent grills
  7. Removing concrete blankets from sidewalks
  8. Installing electrical trim in kitchen
  9. Preparing stucco to receive cap around radius wall
  10. Installing marmoleum flooring in classrooms, kitchen, & kitchenette
  11. Grading exterior to prepare for hardscape
21,174.25

Number of hours contractors have worked on our project.

To view the latest Building Committee video clip of the progress the contractors are making on our remodeling and construction project

CLICK HERE:



Thursday, February 27, 2020

Week 55 - Wrapping Up

The Building Committee is ecstatic to announce that we have scheduled the long-awaitedWalk-Through/Open House at the newly-refurbished Fellowship building for members on:
  • Sunday
  • March 8th
  • 10 am - 11:30 am  
    • Don't forget: this is the first day of Daylight Savings Time.
Members of the Building Committee and the Design Team will be available to answer your questions.

You will need to park on the street, as we don't have a paved parking lot ... yet.  Please be mindful not to block any of the neighbors' driveways. 

Enter through the gate on the east side of the Fellowship (Ceres Drive) and proceed on our brand new sidewalks to the main entrance.  

Building Project Construction Status

  • Significant Milestones
    • Interior finishing nearly complete
    • Stucco & painting nearing completion
    • HVAC startup underway
    • Landscaping postponed to spring
    • Parking lot paving weather delay until early spring - will delay occupancy
  • Other Major Activities This Month
    • Continuing floor tile and carpet installation
    • Cabinets installed in kitchen
    • Bathroom fixtures installed
    • Finishing painting interior & exterior
    • Gutters installed
    • Dais work nearly complete
    • Hearing loops installed
20, 782.25

Number of hours contractors have worked on our project.

To view the latest Building Committee video clip of the progress the contractors are making on our remodeling and construction project
click here: